By this time next year, Kingston, Ontario’s long-awaited third bridge crossing should be open to drivers, pedestrians and cyclists.

Work on the $ 180 million bridge linking John Counter Boulevard and Gore Road remains on time and on budget until the second year of three-year construction.

Despite the COVID-19 pandemic and the rules and regulations that accompanied it, the crossing continues to take shape. And for those associated with the company, the last few months have been productive.

Read more:

Kingston’s third bridge is now 60% complete, on track for the 2022 opening

“(The) project team is excited about the current situation of the project. A large part of the substructure, so all the girders, the concrete girders in the access sections, are finished, ”Deputy Commissioner for Major Projects Mark Van Buren said Thursday.

The story continues below the ad.

“The main steel tranche is complete now and we are now into the coming fall months.”


Click to play video: 'Kingston Third Crossing Update: Superstructure Continues to Join Even During Pandemic.'



Kingston Third Crossing Update: The superstructure continues to bond even during the pandemic.


Kingston Third Crossing Update – Superstructure Continues to Attach Even During Pandemic – May 11, 2021

And that includes work on the bridge deck.

“That will be an activity in the project that will be with us for several months. We’re going to try to get most of those tranches before the end of this year and then complete those tranches work. in the spring of next year, ”Van Buren said.

Read more:

Delays in the global supply chain, shortages could drive up prices and limit options on the shelves

While there have been no major construction challenges, Van Buren returned to the pandemic and how the work is being done in these less-than-ideal circumstances.

The story continues below the ad.

“You know, what has impressed me so far is the people; it really has been a fantastic team effort. Everyone that shows up here to work every day on this scene comes with a passion, and that as an owner, as a representative of the City of Kingston, is just fantastic to see. “


Click to play video: 'Kingston's Third River Crossing Name May Reflect Area's Indigenous History'



The name of the third crossing of the Kingston River could reflect the indigenous history of the area


Kingston River Third Crossing Name May Reflect Area’s Indigenous History – July 2, 2020

A short list of names for the bridge, reflecting and celebrating the stories and contributions of indigenous communities in this region, both past and present, will be released sometime this fall.

© 2021 Global News, a division of Corus Entertainment Inc.



Reference-globalnews.ca

Leave a Comment